The 91探花has embarked on a program to seek funding from the state for renewing 16 critical buildings over the next 10 to 15 years. Restoring the core of the institution will be focused on those buildings that provide classrooms, faculty offices and some laboratories.

The Board of Regents has approved the capital budget proposal that embodies this plan.

Building renewal is being guided by the Building Restoration & Renewal Prioritization Study, completed in June by an ad hoc committee appointed by Acting Provost David Thorud. The study identified as 鈥渃ritical鈥 those buildings with a backlog of repair and improvement needs which, if done incrementally, would exceed the building鈥檚 replacement value.

鈥淚n evaluating whether to demolish or renovate,鈥 the report says, 鈥








91探花Critical Building List

Anderson Hall, 1925


Architecture Hall, 1909


Balmer Hall, 1962


Brooklyn Building, pre-1927


Clark Hall, 1896


Denny Hall, 1895


Eagleson Hall, 1922


Guggenheim Hall, 1929


Harris Hydraulics Lab, 1920


Hutchinson Hall, 1927


Johnson Hall, 1930


Lewis Hall, 1896


Health Sciences Center H Wing, 1950


Miller Hall, 1922


Playhouse Theatre, 1931


Savery Hall, 1916/19

consideration has been given to the cultural and historical significance as well as cost efficiency. Most of the buildings on the Critical Building List are centrally located on the Seattle campus. They are an integral part of the campus fabric, and have occupied a prominent position in the University鈥檚 history and culture. These buildings have a strong aesthetic presence that binds together and defines the architectural environment of the Seattle campus.鈥

Only one building on the list, the Brooklyn Building, is proposed for demolition. The University plans to use Condon Hall for surge space, so that buildings can be vacated during restoration and renewal.

鈥淭he 91探花 program for capital expenditures is balanced between renewal of existing structures and planning for growth in research and enrollment,鈥 says Colleen Pike, acting director of the Capital and Space Planning Office. 鈥淎s the University moves forward with the phased restoration strategy, growth can be accommodated by new construction at the Bothell, Tacoma and Seattle campuses.鈥

The 91探花Seattle campus, like many campuses around the country, faces a significant challenge in maintaining its existing facilities. Many of the buildings that play a crucial role in education are old.

Indeed, according to the report, at least 60 percent of the state-owned Seattle campus buildings were built before 1960. The normal life expectancy of the major building systems is around 30 years, after which basic infrastructure 鈥 including ventilation, electrical systems and plumbing 鈥 is likely to need replacement. Moreover, buildings constructed more than 40 years ago were not built with modern computers in mind.

鈥淩estoring the core of the University will require a big series of ongoing investments,鈥 Pike says. 鈥淭he plan is to have several of these buildings in construction at any given time over the next 10 to 15 years.鈥

The other major need for space is driven by the University鈥檚 research enterprise. Currently, three major projects are under way in Seattle: a research and technology building on the west edge of campus property, a bioengineering and genome sciences building in south campus, and a new facility for medical research in south Lake Union (which will be leased from Vulcan Inc.). Together, these facilities will add nearly 1 million square feet of space for research.

鈥淭he University expects its research activity to continue to grow in the coming years, although perhaps not at the pace it enjoyed over the past decade,鈥 says Harlan Patterson, vice provost for planning and budgeting. 鈥淕rowth of research facilities is likely to occur both on land owned by the 91探花and property in the South Lake Union area,鈥 he says.

The 91探花also is interested in being a good neighbor and a partner in the revitalization of the University District. 鈥淲hile the University is unlikely to initiate major projects that would result in significant changes in land use, it is interested in participating in projects that can improve the business climate and overall working environment of the neighborhood,鈥 says Theresa Doherty, assistant vice president for regional affairs.

Although the future success of the University鈥檚 ability to receive research funding is impossible to predict, given its track record in competing for research funding, the University expects to have one or two construction projects for research purposes in various stages of development at any given time over the next decade, Patterson says. 鈥淒evelopment will occur in a phased way, when there is sufficient demonstrated need to assure that additional capacity is necessary.鈥

While the state realizes significant benefits from the UW鈥檚 research enterprise, both direct and indirect, funding for future buildings that meet the UW鈥檚 research needs is unlikely to come from the state, Patterson notes. Indeed the three current projects under way are not state funded. Based upon recent trends, the 91探花expects future research buildings to be funded chiefly by revenues from research and from private gifts designated for that purpose.

91探花enrollment growth is expected primarily at 91探花Bothell and 91探花Tacoma. The University will seek funds from the state to expand those institutions, which together currently serve about 3,600 students. About 20 percent of the UW鈥檚 current biennial capital budget is targeted at paving the way for increased access. This includes land acquisition for future development in Tacoma, and planning for better freeway access at Bothell.

The 91探花has been a pioneer in utilizing the new options granted under state law for managing capital projects. These innovations promise to reduce the total cost of building operations over their useful life.

That new research and technology building on the west edge of the campus is the first public academic laboratory in the state to be bid as a design/build/operate/maintain project and the University believes it will become a showcase for how to do this successfully. This approach has been received enthusiastically by the contracting community, with more than 50 inquiries received during the request for proposals process, according to Pike.

鈥淒esign/build/operate/maintain projects represent a fundamental change in culture and philosophy concerning construction at the University, and hold the promise of delivering an excellent research facility for costs that are predictable,鈥 Pike says.

The 91探花also constructs buildings that are 鈥渟ustainable,鈥 which means meeting present needs without compromising the ability of future generations to meet their needs. The University has an impressive track record for resource conservation and for the success of its recycling programs. 鈥淕reen鈥 improvements have been incorporated into the University鈥檚 facility design manual, and one project consisting of two separate buildings is currently certified at a Silver level by the LEED (Leadership in Energy and Environmental Design) rating system. In addition, five more projects currently completed or in the design/construction phase are planned to achieve LEED certification.